How use weeks in Advanced Roadmaps for estimation

Michał August 8, 2023

Hey,

do you know any option to show estimation in weeks instead of days in Advanced Roadmaps?

thank you

Michał

2 answers

0 votes
Daniel Capizzi
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 28, 2023

Hi @Michał

Unfortunately Advanced Roadmaps doesn't support using Weeks as an estimation unit - only Hours or Days are supported for time based estimation. I believe the reasoning for this is that in the agile methodology a task that will take multiple weeks would typically be broken down into smaller tasks.

Sorry that I can't give you a better answer here, but if you'd like to request this as a feature the best option would be either through the "Give Feedback" button in the header of your plan or by raising a feature request at jira.atlassian.com.

Cheers,

Daniel

0 votes
Himanshi
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 8, 2023

Hello @Michał , 

Welcome to the community !

I see you are looking for assistance in changing the estimation from Day to week. I noticed that a similar query has been answered here. 

Please consider going through it and let us know if you have any followup queries. 

Hope it would help you. 

Have a great day ahead!

Michał August 8, 2023

Hey @Himanshi

thanks for answer, could you please share link once again? It doesn't work.

thanks

Michał

Himanshi
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 15, 2023

Hello @Michał , 

Apologies for keeping you awaited. 

Here is the link of the community: https://community.atlassian.com/t5/Advanced-Roadmaps-questions/Show-calender-weeks-in-Jira-advanced-roadmap/qaq-p/1739033

Please try to access and let me know if it works.

Michał August 15, 2023

Hey,

thanks for reply.

Thread you mentioned is about timeline and it's values on it.

Need my project came with is unit of estimation. That is shown in advanced roadmaps fields columns.

You can choose between:

Story points

Hours

Days

 

So question is if weeks could be also applied as estimation units :)?

Himanshi
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 2, 2023

Hello @Daniel Capizzi 

No, the weeks can't be applied as current by product design Jira offers only three units i.e Story Points, Days and Hours as estimation.