Hi!!
I am interested in multi-project management with Gantt Chart. I wanted to understand if possible to have timelines based on certain conditions: staff availability (hours and days) and project daily time-load
Example
Given data: 8h/day and 5 days/week working day. The task of the project: 8h
I assign the task to a collaborator (Frank) who works on multiple projects. To this specific project he can dedicate only 3h/day for only 2 days a week (Mon and Wed). By assigning the 8-hour task to Frank in other project management software I looked at I will have a representation on the timeline of 1 day only (since the task is 8 hours). Instead, I would like to see the task automatically spread in 3h/Mon, 3h/Wed, and 2h/Mon for a total of 8h in 8 days.
Is it possible to have this result in Trello? How?
Thank you!
Federico