The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Import updated cards?

EMD Accounting
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 10, 2025

What power up can we use to mass update existing cards and dependencies? Ex. I want to push the due date out for 100 cards by 1 day (they already exist) and (in the same upload) would like to specify some dependencies between existing cards.

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Deleted user
March 11, 2025

Hello @EMD Accounting 

The PowerUp you seek is called Bulk Actions.

It can mass change due dates, but I don't know what you mean by 'dependencies' between cards, so you will have to review the features of the PowerUp yourself to see if it can change whatever that dependency thing is.