How do you remove a card on Gantt Chart in BigPicture without deleting a card on the Trello board?

MK
March 16, 2021

Is there a way to remove a card or list from the Gantt Chart in BigPicture so the Gantt Chart only displays selected cards or list that is from the main Trello board rather than displaying all cards and lists from the Trello board? Much help is appreciated, thank you. 

1 answer

1 accepted

0 votes
Answer accepted
Adam _SoftwarePlant_
Atlassian Partner
March 17, 2021

Hello @MK 

When it comes to the described situation, the current logic between Trello Board - BigPicture is that each and every list and item created on Board will be synchronized back to the BigPicture app. The good news is, that we already have a task in our backlog created in order to enable the filtering of synchronized tasks - please kindly take a look at the link below:

Filtering Trello cards on Gantt

As a workaround, you can try to "Archive" the unwanted cards/lists on your Trello board, since such items will not be displayed in BigPicture list of tasks.

Best regards,

Adam

MK
March 18, 2021

Thank you Adam! You are very helpful!