The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Can't copy across Custom Field and Label with wildcards

Nelson de Sousa
July 16, 2026

Hi there,

I can't seem to make this automation work. The label copies across as expected, but not the Custom Field - Priority.

Thanks for any help in advance. 

when an item is added to a checklist in a card in list "WORK IN PROGRESS" with the light yellow "{*}" label with custom field "Priority" set to "{*}", convert the item to a linked card in list "TASKS", set custom field "Priority" to "{wildcard2}", rename the card to "{cardname} | {triggercardname}", add the light yellow "{labelwildcard1}" label to the card, and add the purple "TASKS" label to the card

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

3 votes
Answer accepted
Nelson de Sousa
July 16, 2026

As I posted this, I noticed my error. I'll leave it up as a good case study of what you can do with the "wildcards" automation.

My error was that I had set the Priority field to "wildcard2" instead of "wildcard1". 