Tracy Brigham December 20, 2022

Hi All,

 

As per below screen shot, I want to be able to remove completed tasks from the view.  The team from a deadline date point of view only wants to see active tasks by date.  Is there a setting that I can remove completed checklist task from the calendar view?

 

Screenshot 2022-12-21 175939.png

1 answer

0 votes
Tracy Brigham December 21, 2022

Hi All

 

I managed to find the answer myself but would like to share in case anyone else has had trouble finding it.

 

In Filter click on the Show more options in the Due Date filter and at the bottom are two check boxes 

  • Marked as Complete
  • Not Marked as Complete

Screenshot 2022-12-22 163504.png