My case:
- I create a story with multiple sub-taks.
- Each sub-task has an original estimation. The cummul of the time of each sub-task is visible in my sprint overview on Story-level. This is okay.
But when I want to capture data via "search issue", the column "original estimate", "remaining estimate" and "time spent" remains empty on Story-level. The time is only visible per each sub-task individually. I don't need the whole details of this, I want to see it based on the story. Is there a way to track this?
Hi @Elke Defrere ,
you can do this by adding column " Σ Original Estimate " to your search : it will add the time estimated for your sub-tasks to the parent task. See below screenshot :
Let me know if this helps,
--Alexis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
While I was looking for the answer I found it thanks.
Is there a way we can sum up all the Σ Orginal estimates. and display the value.
Something similar to this filter
Project = "ABC" and Issue type(Story,sub task) and issueFunction in aggregateExpression("Total timespent for all Issues " , "timespent.sum()")
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.