The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

sprint report shows under the completed section only one status

Avivit Zamir
September 30, 2020

sprint report shows only status that we added manually as completed - called UAT

if we want to define more status as a complete, is that possible? 

Global-CSE-Agile-Board-JIRA (2).png

Customer-Success-JIRA.png

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Jack Brickey
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 30, 2020

The sprint report works from the right most column. If you place 3 statuses in that last column then they will all be considered done.

Avivit Zamir
September 30, 2020

thanks for the quick answer. 

I have the status: task ready in the last column but still, it's not shown in the sprint report. any other reason can be? 

Global-CSE-Global-CSE-Agile-Board-JIRA.png

Avivit Zamir
September 30, 2020

i found the problem. thanks! 