The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

priority change SLA impact

sunita yadav
April 27, 2018

IN JIRA service desk i faced an issue:-

1. Incident was raised as S2 and SLA response time was 30 m. 

2. But as per analysis and discussion with customer we changed it from S2 to S3, ideally response time should have changed to 10h. 

But it had not happen. 

Please suggest! 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Francesc Arbó
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 27, 2018

Hi @sunita yadav,

 

Please, make sure this Response Time SLA is not completed. An SLA can't be changed if it's completed. Check the goals configured to verify if the JQL is correct.

Jack Brickey
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 27, 2018

Agree that is the first step. Check the history and see if the time of sev change was not greater that time of creation +30m