The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Upgrade from JIRA v7.1.4 to JIRA 7.43

Esther Ferguson
August 29, 2017

Hi All,

So, roughly how long would an upgrade from JIRA v7.1.4 to JIRA 7.43 typically take? 1 hr, 2 hrs? Or do you need more information to make this determination.

I'm just looking to see how much time you would allocate for yourself to upgrade JIRA, so that I can notify my customer's on how long JIRA would be down for.

Thanks,
Esther

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 29, 2017

Less than 5 minutes when you've only got a few issues, hours if you've got hundreds of thousands.  The upgrade doesn't make vast changes to the database, but it needs to re-structure it in places which takes time proportional to the amount of data in the tables it's changing, and then re-index, which is roughly proportional to the number of issues you've got.

Esther Ferguson
August 29, 2017

Thank you!