The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Pause SLA based on Status in another workflow

Daniel Ballinger
November 8, 2020

Hi all,

I am currently working on setting up some SLAs within Jira service desk Cloud. 

 

My level 3 escalation sits in my problem workflow, I want to be able to pause the SLA in the incident workflow if the status in the problem work flow is Level 3 escalation. 

Can this be done and if so how would i go around doing this? 

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Gökçe Gürsel {Appfire}
Atlassian Partner
November 8, 2020

Hi @Daniel Ballinger ,

You can add a status (say "Pending Escalation") in your "teh incident" workflow and set up an automation rule to transition the issue to "Pending Escalation" during lvl 2 escalation and use this status to pause your SLA.

You can set up another automation to transition the issue from "Pending Escalation".

Please let me know if you have further questions.

Regards,

Gökçe

Daniel Ballinger
November 9, 2020

Hi,

Thanks for the reply and didnt really want to have to change the workflow to encorporate this but i guess i will have to due to the issues raised on the below.

 

https://jira.atlassian.com/browse/JSDCLOUD-2297

Daniel Ballinger
November 9, 2020

I have accepted the answer as a workaround.

It does mean capturing the status of the problem workflow within the incident workflow(In my case) and then setting automation to trigger the tansition.