The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Is there some way in JIRA that I can register the advance of an issue in percentage?

Daisy Gaona
September 26, 2017

Is there some way in JIRA that I can register the advance of an issue in terms of percentage?

I know that JIRA gives you the information about the time remained (based on estimated time), but I'm not talking about time. I'm talking about the progress of a task. Because you may have sub-estimated a task, and it shows that you're using all the time but the task is not completed. 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 26, 2017

On the parent issues, you can toggle the inclusion of the sub-tasks on and off.  In report (mostly the issue navigator) there are a set of "sigma" fields for pulling the accumulated numbers out.

If that is not what you mean, then you are going to need to explain how you are measuring "progress" - what's the quantifiable numbers you are putting on issues?

Daisy Gaona
September 28, 2017

Now I do not have any field to register the advance, I just have the estimated and the remained time, but, again, If you made a bad estimation of the task, and you're using all the time but the task is, -for example- at 60% (not completed), I don't have the way to inform that.  I think I can create a customized field for that purpose. 

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
October 3, 2017

If you have one of the scripting add-ons, then yes, a scripted field could easily work out a percentage from time estimated vs logged or remaining.  You'd want two fields - one for each issue, and one for parent issues that accumulates the child issue values.