The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do I trigger an automation 5 days prior to due date?

Margaret Winward
Contributor
October 22, 2020

I am trying to create a task 5 days prior to the due date in Jira Service Desk. The JQL I tried triggers the automation 5 days after the due date. What would be the JQL?Screen Shot 2020-10-22 at 8.12.44 AM.png

 

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Velizar Borisov
Community Champion
October 22, 2020

Hi Margaret, 

It should be the way you used it. "due = -5d" will always give you the issues with

'due date' = 'current day' - '5 days'

The only thing that comes to my mind if you accidently forgot to save your automation rule.

Besties,
Velio

Margaret Winward
Contributor
October 22, 2020

That's what I thought. You got me thinking so I just removed the "-" and it now runs 5 days prior to the due date so it is opposite of what I thought it should be doing. Thank you for helping me stir my thought process.