The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How SLA work when has 2 start point

my
November 25, 2019

Hi all, please help me about SLA

In matrix time  I select 2 items for Start

1.  Issue created

2. Assignee: change

Stop when Enter status: Done

SLA goal is 1h.

Step:

I created ticket when SLA counted 30min I changed assignee but SLA count didn't recount 

I think when I changed assignee then SLA should recount

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Olga Videc
Community Champion
November 25, 2019

Hello @my 

You mean the SLA should reset?

No, it doesn't work that way SLA is triggered by one of those events, and by default, it can't be reseted.

If you want SLA to reset you will need a plugin.

BR, Olga

my
November 25, 2019

Thank you very much Olga.

I think SLA should reset.

So If SLA has more than one event start then SLA start counting when one of event occurs 