The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Due date doesn't reflect SLA

Matthew Cascio
October 30, 2020

The due date and SLA time remaining for issues in my Service Desk do not reflect the SLA configured in settings.  For example, see attached screenshots. Let me explain what you'll see:

The issue in question was resolved yesterday, 29/Oct/2020 5:00PM

The SLA "Time to close after resolution" time remaining for that issue says 1w 4d and when hovering on that text, the due date shows 11/Nov/2020 5:00PM

However, this SLA is configured as 72h (3 business days on M-F 9a-5p schedule) so the Due Date should really be 3/Nov/2020 5:00PM

What causes this discrepancy....or am I misunderstanding something?

Thanks!

Matt

Screen Shot 2020-10-30 at 8.58.28 AM.pngScreen Shot 2020-10-30 at 8.53.57 AM.png

2 answers

2 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Flavien Gache
Community Champion
October 30, 2020

Ok so you set your SLA with a goal of 72h.

The hours in SLAs are only counted down during working hours. In your example, it means that your only 8 hours a day will be counted down of your SLA per day.

In other words, it means that the goal you set (72h) represents :

72/8 = 9 days

In your case, you could change the calendar to be 24/7 if you only want to count 3 day of SLA. Or you can "convert" your 3 days, which in your case would mean a goal of :

3 x 8 = 24h goal. 

Bear in mind that hours are only substracted during the hours set in your calendar ;) 

Let me know if you managed to solve your problem.

Matthew Cascio
October 30, 2020

Thank you!

Like Flavien Gache likes this
1 vote
Answer accepted
Tessa Tuteleers
Community Champion
October 30, 2020

Hi @Matthew Cascio , 

the SLA says 72h on a monday to friday 9-5 schedule. Thats 72hours on an 8h/day, 5 days a week schedule. 

So 72 hours makes that 9 (72/8) business days. Starting yesterday (thursday) end of day would make that  9 businessdays later or wednesday 11/11.

If you want to have 3 days, that would be 3*8 -> 24 hours. OR use a 24h businessday calendar and keep the 72hours SLA.

 

Good luck! 

- Tessa

Matthew Cascio
October 30, 2020

Got it.  That makes sense.  Thanks!