I need to create the following configuration - projects and tasks with no SLA, but I need sub-tasks (in two types) with SLA. How can you achieve this effect?

1 answer

0 votes
Jack Brickey
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 20, 2020

you should be able to accomplish this simply by defining the Goals of your SLA and incorporating "issuetype = subtask".