Automate due date based on story points and start date

iatkinse
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 7, 2025

I want to know if its possible based on below criteria:

---This part already automated--

Story status moves from ToDo to In-Progress
Start Date date added 

---Need to automate---

I want to take Story Points and come up with a due date

Example: 1pt would equate to 1-3 days worth of work, due date would be 3 days from start date

1 answer

1 vote
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 7, 2025

Hi @iatkinse -- Welcome to the Atlassian Community!

Yes, that is possible using the automation date / time functions, and either conditional logic or a lookup table to map the values.

However, I recommend trying something different as Story Points are normally used as a relative measure rather than as only a time-based one.  Perhaps consider switching to the time tracking estimation rather than with Story Points.  Then the "Original Estimate" field could be used to forecast the Due Date.

Kind regards,
Bill

iatkinse
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 7, 2025

 

Hmmm not sure where original estimate comes from but these are the fields I have access to, anything else outside of these are not feasible to be turned on. I don't know if that helps.Screenshot 2025-03-07 151439.jpg

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 7, 2025

I was describing enabling the time tracking features.  Once those are enabled, the Log Time features allow using fields such as Original Estimate.

https://support.atlassian.com/jira-software-cloud/docs/what-are-time-estimates-days-hours-minutes/

 

Please discuss this approach with your project admin and team before considering this change.