The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

I can not "complete the sprint"

Shereen al Nimri
October 6, 2024

 

 

 When I chose the option "complete the sprint", this message popped up

"This sprint contains:

0 completed issues

21 open issues"

although the sprint is completed, within all tickets and tasks included, and all the status for the tickets is "done"

What should I do to make all done tickets in completed issues so I can close/ complete the sprint

 

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

2 votes
Answer accepted
Walter Buggenhout
Community Champion
October 6, 2024

Duplicate of this question. Replied to the other one. 