I can not "complete the sprint"

Shereen al Nimri October 6, 2024

 

 

 When I chose the option "complete the sprint", this message popped up

"This sprint contains:

0 completed issues

21 open issues"

although the sprint is completed, within all tickets and tasks included, and all the status for the tickets is "done"

What should I do to make all done tickets in completed issues so I can close/ complete the sprintdone.jira.PNG

1 answer

1 accepted

4 votes
Answer accepted
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 6, 2024

Hi @Shereen al Nimri and welcome to the Community!

Is the Done status in the rightmost column of your board? That is how a scrum board determines if issues are done in a sprint. If there is a column to the right of your done issues, that is most likely the cause.

Hope this helps!

Shereen al Nimri October 6, 2024

done.jira.1.PNG

Shereen al Nimri October 6, 2024

yes it worked, thank you very much 

Like Walter Buggenhout likes this