The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

story burndown at epic level in jira align

manish a
Contributor
November 6, 2023

For a epic in jira align I want to check the progress.

Is it possible to see the story burndown at epic level in jira align 

or any other view which shows the progress 

 

can i can see the status which shows the total story points and total story points accepted. 

 

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Aline Chapman
Contributor
November 6, 2023

From Jira Align, open a (Portfolio) Epic and click on: Show More > Epic Planning > Show by Story Points. This report provides a burndown of items tied to the Portfolio Epic. See if this helps you.

manish a
Contributor
November 9, 2023

excellent. Thanks for the quick response. 