The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Work tree initiative count number after narrowing to CI still includes all CI's.

Theodore Gill
February 7, 2024

Work tree  - Narrow to Program and Cycle Increment  - under Program Backlog – Initiative – Items count is from all Cycles – why doesn’t this number reflect just the Narrow to Program and Cycle Increment count?

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Jamie Giantonio
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 7, 2024

@Theodore Gill if you are using the "top down from initiative" view and selecting Narrow to Program and Program Increment, only the child items are affected. When toggling this on/off you should see a difference in your story counts.

 

From the Help page for work tree: To narrow your work tree report results, switch on the Narrow to Program and Program Increment toggle in the upper-right corner:

  • The toggle is available when using the Top-Down, Team, and Theme Group views.
  • When the toggle is switched on, only those child items that belong to the selected PI and program are shown