The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Initial Estimate Greyed Out on Epic

Stephanie Davis
Contributor
February 22, 2023

On Epics, the Initial Estimate field is greyed out.  How does it get set originally?  I'm not seeing a way to estimate on the the add or edit screens.

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Jamie Giantonio
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 22, 2023

@Stephanie Davis Initial estimate will be greyed out once the Epic is assigned to one or more PI's. You will then see the PI estimates for any PI's associated. If you want an overall estimate for the Epic, set the intitial estimate before it is assigned to Pi's.

1 vote
Samit Mehta _321 Gang_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 22, 2023

Hello @Stephanie Davis

The Initial Estimate field is greyed out when you specify Program / Planning Increments (PIs) for the Epic.  The "Initial Estimate" is the overall estimate (across PIs), and so when you specify the PIs for the Epics, it gets greyed out and you are only able to specify estimates for each PI.