The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Identify missed stories in the sprint

manish a
Contributor
September 13, 2023

in jira align program room i can see sprint 215: 131 out of 135 stories complete. How to know the stories which were actually missed. 

 

 

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

2 votes
Answer accepted
Jennelle Stearns
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 14, 2023

@manish a one way you could do it is to go to the Stories Grid (not backlog) (New Nav - Items -> Stories, filter by the Program and the increment (same as what you are using for Program Room) and State not= Accepted.  Select More Actions and export the stories.  Then filter on the column called Sync Sprint (select Sprint 215).  That should show you the stories in that sync/anchor sprint that weren't completed.

manish a
Contributor
September 18, 2023

Great. This helps. 

 

however if sync sprint filter option was available in the grid view itself then it would have been much much easier.

manish a
Contributor
September 18, 2023

one follow up questions. if in jira they have moved the story to subsequent sprint post that sprint start. will it also get counted here.  

0 votes
Tina Behers
September 18, 2023

@manish The work in progress report (team level reports) will also provide you detailed info on stories 