The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do you use MISSED status in Objectives?

Marcie Mierz
September 21, 2022

I can't seem to find any documentation that explains what the status of "missed" represents for Objectives. Is this a phantom value that crept into our configuration or an earlier status that has been depreciated and isn't worth mentioning anywhere?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Nohma Abboud
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 4, 2022

Marcie,

  • Missed: Indicates that the goal described in the objective was not reached in time.

 

hope this help

Nohma Abboud

Marcie Mierz
October 11, 2022

that makes sense, but if the objective was expected to be delivered mid PI, then what happens?  do you just change the expected date to shift the objective out along the PI timeline and it will always maintain the missed status even when it's delivered?  

Like Nicholas Taylor likes this
Nicholas Taylor
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 10, 2023

Hi @Marcie Mierz - If the Objective was planned to be completed within the PI, but it didn't occur [for whatever reason], then it gets re-labeled as "Missed" per what @Nohma Abboud shared.

That Objective does not rollover into the following PI. It stays for tracking purposes and overall ART metrics, etc.

If the work (ie. Feature) is going to rollover into the the following PI, then you would simply create a new Objective.

 

Hope that response helps and is of value!