The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do 'Process Steps' work when you split a feature

Bob Hunt
Contributor
January 29, 2025

Our Features go through a maturity definition phase from initial definition through to Development Ready (i.e. Feature Definition --> Feature Refinement --> Development Refinement --> Development Ready) At Dev. Ready the feature can be worked on in a PI.

When we split the feature it seems that the original Feature's 'Process Step' is not carried over to the split feature. Is this a bug? or is this expected behavior?

Thanks in adavance!

Screenshot 2025-01-29 123546.png

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Allan Maxwell
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 10, 2025

Yes, that is the expected behavior.  When a Feature is split, it is essentially like creating a brand new Feature.  The state and process step is set to the "initial" values.  Ideally, the new Feature would then be prioritized against all other possible Features in the backlog.