I have a global rule to sum up estime time from sub tasks, to tasks, to epics and i wanted it to also go to initiative, but it does not work and i dont under stand why.
here is my rule
It is a company wide software project with all 4 tiers.
as you can see it works until Epic
as you can see here jira sees the epics as child items to the initiative
Hello @David Larsen
Welcome to the Atlassian community.
Is the rule being triggered when the Epic is updated? Do you see an entry in the Audit Log for that execution?
If you do, please share the details of that with us.
Welcome to the community.
You need a second rule for that action, this can't be done in the same rule.
See this related community posts about this.