The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results forĀ 
Search instead forĀ 
Did you mean:Ā 

Field Value change for status change first time

Brandon Huckaby
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 12, 2020

I am trying to create an automation that changes a field value based on the status change of a ticket. My example is when a ticket goes from "In Review" status to "UAT" I want the Finish Date to change to current date.

I currently have this working however I only want this to happen on the FIRST time this status changes from "In Review" to "UAT". The way my workflow is setup tickets can jump back and go through the Review process again. 

Thanks for any help or advice

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Curt Holley
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 12, 2020

You can set the transition to only update when a ticket goes from "In Review" status to "UAT" and not any other status (which a presume you have done). So if you add into the automation that it only updates the "finish date" if it is empty as a condition, would that do it?

Only problem then is, if it does cycle through  "In Review" status to "UAT" more than once, it will still have the 1st cycle date as the finish date.

Helpful? perhaps???

Brandon Huckaby
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 13, 2020

Yes, I only want the finish date to update the first time it goes from Review to UAT. Right now if the ticket cycles through again the date gets updated again. I will look into how to only set if empty. Didn't think of that.

Thanks!