The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do you edit or set the target date for a project in Atlas?

Drew.Morgan
Contributor
July 17, 2023

Hello!

I am trying out Atlas for tracking our product priorities for the upcoming quarter. On the first project, I synced it with a related Epic from Jira, and when it synced, it set the target date automatically.

For the rest of the projects, when I sync, it's not setting the target date. 

How do I manually edit the target date on a project? Is there a permission thing that I'm missing?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Mark Parnell
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 21, 2023

Hi Drew,

Thanks for the feedback - I'm not sure why it's not syncing with the project. I can tell you that to manually change the target date, you need to post an update for the project, with the rationale being that changes to a target warrants an explanation to followers.

Let me know if this works and then also updates the Due Date on the Epic.


Thanks,


Mark

Margaret
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 14, 2025

It would be really helpful if you could set an initial target date on creation of the project - that initial target isn't a project update.