Hello, I purchased JIRA and Portfolio for Jira (Server version for 10 users) I perform the below article. Howerver, I can't search Portfolio for Jira. How can I search the p...
Hi, We are currently using Epic / Story architecture and want to add feature level. Is it possible ? As I am administor of the project I don't see where it's possible. Thanks ...
Portfolio lets one group tasks into Initiatives. This hierarchy is visible in the Portfolio Roadmap page, but also when you view the Initiative issue - one sees a 'Child issues' section with the init...
I've gone in and set up themes and initiatives in portfolio, which is great. In planning view, though, it only allows me to choose two levels. https://t.co/GwZEWIs0gN Is it possible to view...
I can see the Target Start and Target End Date in customfield table but those values are not storing into customfieldvalue or customfieldoption Any one knows where Target Start and En...
I created shared teams, and I see the Team on my issues, but how can I filter or show these teams on my views and reports? Is team reporting only available within Portfolio?
I removed an Epic that aligns to an existing initiative and realized I couldn't easily recover it...what is the best way to recover an epic or user story when removed?
We've just recently upgraded Portfolio to 3.9 from 2.21. We found that none of our existing plans could be upgraded to the new interface. While we couldn't find any documentation to corroborate, we...
Is there a way to show the % Progress on a Kanban board card? We have the Portfolio configuration in place where an issue has child issues, progress is calculated as follows: Progress = Number ...
I know I can create custom 'issue types'. Can I create a customer issue hierarchy using these new issue types? For example, I need to create a new issue type called 'Feature' and I need t...
When Portfolio For Jira 3.0 will be available for Cloud version? Is Atlassian considering this?
Hi, I've got 6 Portfolio plans that use filter by label to display the cards related to that plan. It seems the filters are only being applied at a per-user basis: when I log in, the filters...
Hi, In my team, we have the releases fixed (time) and the amount of scope fixed and I would like the capacity to adjust according to these two. As we can see in the following screenshot, we ...
Hi, How is overload calculated? Is it the teams capacity in the 23 extra days? Regards Louise
Hi, I don't understand why Portfolio tells me my colleague is overbooked when he is not. In the first screenshot, I can see that in week 42 there is a yellow bar and when I hover over it, i...
After updating Portfolio to 3.9.0 all issues are showing a warning when the due date is the same as the target end. Is there anyway to fix this? All our planned issues are now shown with a warning......
I have Jira portfolio and Jira Service desk, I create a plan including a Jira Service Desk project, Defect : shows tasks wich are in status "Résolu" (solved), whereas it should be able to filter ou...
Dear Team, I've created Epic with tasks and sub tasks inside it. I would like to know how it is possible to change Epic status automaticly to 'On Going' once a task/sub-task under that Epic started...
Hi All, I would like details columns to be displayed in the scope chart instead of the progress bar. In other words, when you put your pointer above the progress bar you can see the...
Hello, We update recently to 3.0 Portfolio version and we are having some issues regarding the absences days of teams members and the impact on teams capacity. Use case: Team is create...
Hi there, i've setup a plan where i imported 2 JQL queries as they are business projects. in addition to that i've also taken 2 boards of our development teams as source because i wanted to schedule...
When I set up a plan, choose my boards, and then select fixversion, the plan still pulls in tickets that don't even have a fixversion. When I go into the settings to select the releases, all of the a...
How do i assign project start and end in portfolio for JIRA?
where is the "View settings" ? cant fine it ..
When hovering progress bars for initiatives or Epics in Portfolio for Jira Cloud a note appears that displays Completed Story Points and Remaining Story Points. I would like to be able to export the...