Hello,
Seeking help in Jira Plan.
Let's say I have one ticket (ABC) which is blocked by another ticket-123. Since ABC release is dependent on Ticket-123, lets say the end date got changed or by any reason it got delayed. Is it possible to change the start date and end date of ticket-ABC accordingly in Jira Plan.
If it is feasible, what are the steps?
Thanks
Hello @Vandana Mandal
Are you using Jira Cloud or Jira Data Center?
If you are using Jira Cloud you might find this article I wrote helpful. It talks about how to solve the problem you mentioned using Automation Rules.
Updating dependent task's dates when predecessor task date changes
Hello @Vandana Mandal
Were you able to address your requirement with the reference article I provided?