The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

This, like many Jira articles, is missing some steps. How do I get to the graphical scheduler in the first place? This tells me how to configure it, but I can't even find it to get started! Please advise.

PJ Alfrejd
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 23, 2016

This question is in reference to Atlassian Documentation: Using the graphical schedule

This, like many Jira articles, is missing some steps.  How do I get to the graphical scheduler in the first place?  This tells me how to configure it, but I can't even find it to get started!  Please advise.

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Post a new discussion

105349
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
May 23, 2016

Hi PJ!

Try this:

  1. From your JIRA dashboard, click on the Portfolio button at the top of the screen.
  2. Click All Plans.
  3. From there, either choose the plan you're after, or click the New Plan button in the upper right.
  4. Once on your plan screen, note at the very bottom there's the schedule, (see  screenshot). 
  5. From there, you can click on the '...' and drag it up to reveal all the buttons mentioned in the documentation.

Let me know if you run into any issues!