In portfolio there is 2 fields called scheduled start and scheduled end. How is this configured? I tried to look in my admin settings but these fields are not in the available fields. Is this something specific to portfolio?
I have custom start and end dates for my project Epics which I would like to use in Portfolio, why is this not an option? And lastly, what is the point of adding in custom fields into Portfolio if you can't use them for portfolio management? The whole point of this view is to manage dates, why is the schedule date field not editable? And why cannot you use your own custom dates instead?
----
edit:
So it looks like Portfolio is only useful if you run SCRUM and build "stuff" based on Release. Meaning if you run Kanban with start and end dates but no Release, Portfolio is useless.. So frustrating..
Solved! Go to Solution.
Thank you Martin. Appreciate the response here. Managed to figure it out in the end with your help. Cheers
Hi Martin,
According to image below, if you move the story to an earlier release, the release's end date should overwrite the computed scheduled end date. However, its not happening in my case. Do you know why?
Thanks
M.