The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Keep task duration constant, when adjusting the start date in advanced roadmap plan.

Ricardo Sanchez
April 12, 2023

Hello,
Could someone please help me with this issue?
Is there a way to keep the duration of a task fixed even when we change the start date on the advanced roadmap plan?
For example, if an issue's duration is three days (DU2-6) and we change the start date (April 24) to one day later (April 25) using the "Start Date" input field, we would like the issue's bar to automatically shift one day to the right while maintaining its original size of three days and All linked and parent issues (DU2-6 to DU2-11) move similarly without adjusting or moving them manually.
The screenshot shows the expected outcome.
I appreciate your help.
Thank you!

AA2023-04-12_22-58-18.jpg

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Ricardo Sanchez
April 20, 2023

Dear Community,

I am delighted to share with you a solution to the challenge I faced. By leveraging the auto schedule feature, I have successfully arrived at a practical resolution.
Please note that the "Original estimate" for each task is one day.

I appreciate your attention to my post and thank you for your consideration.

Best regards,
Ricardo Sanchez

2023-04-20_22-36-13_Auto-schedule.jpg