First of all I can't get any sales person to call me back from Atlassian re our switch from Aha! to Advanced Roadmaps, for a 1000 person user base.
2nd, when I schedule sprint in my projects they do not show up in my plan. They are in a field that says sprint is external.
How do I create a sprint within the plan so that when I'm doing capacity planning and have my view in Teams and Show Capacity mode I can see my current, or future sprints. If I create a sprint in a project i have no control over it in the plan.
Also the dependency flags are not turning red when lead days are negative, why is that?
Hi Earl.
Thanks for the lengthy response. None of this actually helps.
First fo all, we have a licensing agreement and pay a large amount of money to Atlassian. For some reason I'm only given the option of asking the community for help when logged in. We have Premium and I don't seems to have an option of submitting a ticket.
Next, we had your own sales guy reach out to us over and over again. When we finally decided to try Advanced roadmaps, not with any help from him, he simply stopped responding to questions from our company. Divya Rosenberg.
I'm also fully aware of how sprints work and where they get scheduled. I've been a product manager for 16 years, and have used your tools from the early days. This component of advanced roadmaps is just not working as described in your documentation.
I had already read through all of the documentation before I made this post. I don't see any new information I don't already know about. However, the application does not behave as described in your documentation.
So basically this information does nothing to help resolve the outstanding issues before I have to demo this tool the the company tonight.
We are about to possible spend more than $20k with your company and I have to resort to forum for help. It's pretty sad.
Thanks,
Ali
Hi @ali.alavi ,
Check the 3d video on this page for how to get started with capacity planning.
Cheers,
Hi Roi,
Unfortunately watching your videos is not helping either. This is all seems very simple and straight forward. However, Advanced Roadmaps is not performing as described/demonstrated in your videos or documentation. Sprints in projects do not show up in on my plan. No capacity is placed into active, current, or future sprints. As matter of fact only projected sprints are shown when looking in teams view with capacity view is enabled. Projected sprints do not take on any capacity when scheduling issues.
If the tool worked as described I would be okay, but for some reason it does not.
Thanks,
Ali
Same issue here, can't figure out how to create a sprint inside advanced roadmaps, it's all just 'projected sprint'. When trying to update via bulk actions it won't allow me to create new, and the selection list doesn't work.
I had this same problem and figured it out just now based on Earl's answer above.
I went to the "Teams" tab, then go to the Edit option for the team you want to do capacity planning for. Under the "Associated Issue Source", it needs to reference the Scrum Board that the sprints are in. It will not work if the issue source is a Project or a Filter.
I also had the issue of sprints not showing on the timeline. I had forgotten to change the view settings to group by team.
I had the same issue here are my steps to make it work based on Earl's first answer (upvoted):
Once all of these steps were done, my sprints were showing correctly (and linked for further modifications)
Also keep in mind the project board you are linking has to be a "Scrum" and the teams should be "Scrum" teams