How is it possible to move multiple timelines at the same time in Jira Plans?
Example: Delay in the project - all downstream tasks are also moved.
Unfortunately, it does not work via dependencies (blocked by or blocks). Also, as researched, the CTRL/STRG multiple selection does not work either.
Is there an easy way to move several tasks? Many thanks for your help!
Best regards Christian Brandl
Thanks for the Information!
But like you mentioned below - all timelines will be in the same date-range.
Important to me is, that I can shift all timelines with their space between.
Means that they shall have their same duration, like: after workpackage A follows workpackage B.
I have the same question. Despite the fact JIRA could track dependency, but it does not seem to act like MS Project where moving one task would trigger cascade effect to the dependants.
Hello,
If you are using Jira Cloud and if your work items are all part of the same project, then you could achieve this in the Timeline view.
I hope this helps.