I'm currently planning Epics in Portfolio.
We've estimated an epic to take 15 days
When Portfolio automatically schedules it sets the start / end date to be Nov 8/ Nov 19.
I expected the scheduler to slot 3 weeks of time. Nov 8 -> Nov 29 (as it doesn't include weekends)
I believe that it's assigning 11 days because it's assignign two people to work on it. How can I set it up so that automatically, only one person is assigned to an epic?