We are utilizing Advanced Roadmaps to visualize a project structure where the following issues are in place:
We are running into an issue and experiencing a lot of manual work when a task in a phase is delayed. When this happens, the dates are pushed out on the task (start date / due date where applicable), but then our PMs have to do the same for each successive task / sub-task, phase, and so on, due to the one delayed task...
Is there a way to automatically move all successive tasks out based on a move of one of the prior tasks?
Any guidance or suggestions on how this has been accomplished are greatly appreciated!
Community moderators have prevented the ability to post new comments.
Thanks, @Trudy P ClaspillI'll dig into the resources provided. Ultimately we're looking for auto-scheduling of waterfall projects, so perhaps estimates are the missing link.