Hi
When updating a cards due date I want to update the linked card's due date to the same date + 3 days.
I guess Butler is right for the job.
I've got this far.
I think the steps are.
Trigger: on set due date
Action:
Step1: find linked card
Step2: set the same due date on the linked card as first card (can't accomplish this one)
Step3: add 3 days to due date
@Anders it's a bit hacky but you have to do it via a custom field:
when a due date is set on a card, find the first card linked in the attachments, set custom field "Due" to "{triggercardduedate}", and set due on the date in custom field "Due" plus 3 days
Thanks @Iain Dooley I'm still having issues. This is what my rule look like now:
when a due date is set on a card by anyone, find the first card linked in the attachments, set custom field "Due" to "{triggercardduedate}", and set due on the date in custom field "Due" plus 3 days
The rule is enabled. I've tested that the link is correct by just setting due date to now and that works. But my query doesn't work.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Anders maybe check the usage log to see if there are any errors, I just created this rule afresh and it works fine:
when a due date is set on a card, find the first card linked in the attachments, set custom field "Due" to "{triggercardduedate}", and set due on the date in custom field "Due" plus 3 days