HI
I am trying to automate a selection of project boards so a card is moved from a project board when I need to start working on it or it is due, to another board (my to do) board. I can find a way to do this using the date automation and having due dates on my cards.
However, I want to use start and finish dates on some cards for my timeline and also to give myself time to work on bigger tasks but the due date automation only works on due dates. I can create a rule that says move card when I set a start date but it does that as soon as I set the start date but I want it move only when the start date is due.
Any solutions?
Yes, Trello has really provided half a solution with start dates and I wish there was more capability around it. The only way around it is instead of using the due date automations, use the scheduled automations...
every day, move each card starting today/this week....