Rule for checklist item completed: then member of next checklist Item is added & previous is removed

vassovass
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 7, 2023

I want to Create a Rule that when checklist item completed then member of next checklist Item is added and the previous is removed

 

2 answers

0 votes
Dreamsuite Mike
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 21, 2023

This could be done with automation. You would need several things.

  1. A 'lookup' card with the member information
  2. It would have to be that you build the checklist from a checklist template so that on the working card, only when an item is checked, does the next unchecked item get added. 
  3. When it gets added, you could do a lookup for the member card and add the username to the checklist item
0 votes
milynnus
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 7, 2023

@vassovass 

You probably can’t do it without use of some api since you cannot add a member without selecting a specific member while creating the automation. 