Hi, I'm trying to setup due dates for my checklist using no. of days from when the board is created

Witte Group
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 7, 2023

We wanted to have due dates based on when the board/deal is created. For example, I created the board today and added the checklist. I want to have the option to have due dates such as for example - Today, Tomorrow, After 2 Days, After 7 Days, etc. It is essential in our business to have this option. Can you let us know if it's possible? Thanks!

1 answer

1 accepted

0 votes
Answer accepted
Ost September 7, 2023

You can add due dates manually to each item in a checklist, and assign each line to a person.  

If you want to automate it you could with a stock checklist.

You should write the checklist, build out with due dates. This should be in a separate card that's not sitting in your workflow.

And then use Butler Automations to have the checklist (use exact name) from card (URL) auto populate onto a card when drug into a new list. 