I have added 5 cards in a List with their respective due dates. Here's the breakdown of my List.
Card 1 - Due Date 03-06-2022
Card 2 - Due Date 06-06-2022
Card 3 - Due Date 07-06-2022
Card 4 - Due Date 08-06-2022
Card 5 - Due Date 09-06-2022
Now, due to some urgent task Card 0 needs to be added before Card 1 and The due date of Card 0 should be 03-06-2022.
So, I have added Card 0 and its due date 03-06-2022 but I don't want to manually change the due date of the cards in pipeline. I want to shift the due date of pipeline cards automatically to their respective due date.
Please suggest any Butler way to fix his.
Thanks
@Vikash Kumar welcome to the community! Check out the Bulk Actions power-up. It has an option to select multiple cards and shift those due dates by x amount on each one.
@Brittany JoinerThanks for your answer. Seems that Bulk Actions Power Up is a premium add-ons. Is there any way to execute the task with the help of Butler automation.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Vikash Kumar if you have all the cards linked in the "main" card, then i think you could maybe do something like this?