Hi -- I've been using advanced checklists for awhile and there are some things that would make it significantly easier.
1- If I have a card with an advanced checklist, is there a way to assign multiple checklist items to the same user at once? Vs clicking on each checklist item?
2- If I have a template card with advanced checklists, can I set up on the template certain tasks to be completed a specified number of days before the due date? For instance, I have tasks to be completed 3 weeks before the due date, 2 weeks before the due date, etc.
3- If I have a template card with advanced checklists, and a custom date field (call it closing date), can I set up on the template certain tasks to be complete a specified number of days before the custom closing date field? See #2.
Hi @Nora Crosthwaite - welcome to the Community.
I'll answer your questions in the order you've raised them.
I recommend playing around with automation to see if it can help with what you're trying to do.