You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hi, we are ggoing to be updating our requiriments of TSL to 1.2. I wan to be able to tell my customers that this will be done in the future, we dond have a specific date and mabe be thsi will take a few days for all ours services, what is the best way to do this?
Great question! Typically a maintenance should only be used when you know of a timeframe that work will actually be performed on a given component.
For example, when we do work on our own ciphers we post a maintenance notification ~7 days before the maintenance is set to begin. You can see a sample of such a maintenance here https://metastatuspage.com/incidents/zzlx654b4t2x
Hope this helps!