The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

On-call schedules bug found

Deleted user
July 15, 2021

Hi there,

so this describes a tiny bug I found.

1) create a new team, remove routing rules, escalation policies and on-call schedules

2) create an on-call schedule "2021"

3) create a rotation "default" into that on-call schedule "2021"

4) create a rotation "vacation", also into that on-call schedule "2021"

5) now the final schedule section shows both rotations

6) remove the rotation "vacation"

7) still both schedules are shown in the final schedule section

2021-07-15_12h27_29.png

Best regards,
Marco

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Samir
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 19, 2021

Hi @[deleted] !

 

This is intended as the final schedule will continue to show the "history" of that schedule. If you go further into time (i.e. after the vacation schedule is no longer in the history), you will no longer see the vacation rotation in the final schedule. You can move further forward in time by clicking the arrows next to "today", and you should see the Vacation rotation drop off of the Final Schedule.

 

But because it did exist in the schedule at some point during the time frame you are viewing, that is why it is still showed in the final schedule.

 

Hope that makes sense! Let me know if you have anymore questions.

 

Thanks,

Samir