JIRA and Advanced Roadmaps

Clayton
Contributor
July 23, 2024

Hi

Previously when JWM was standalone it was advised not to use Advanced roadmaps with a business managed project.

Now that JWM and Jira Software are integrated does anybody know if this is a restriction? i.e Is there no limitation or consideration if creating a plan for business and software projects?

Thanks!

1 answer

Suggest an answer

Log in or Sign up to answer
0 votes
Stuart Capel - London
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 26, 2024

Hi @Clayton 

 

There's no restriction on using Business Projects as an issue source for Advanced Roadmaps (now just called 'Plans'). You might be thinking of the restriction on 'Team Managed Projects' which still cannot be used in Plans. Only 'Company Managed Projects' can be used as issues sources, if you try to bring in a Team Managed Project, you'll see some text letting you know it's not supported.

 

Hope this helps