the latest tempo timesheet introduced a new tab, "Activity", which includes worklog description & comment, etc.  is there a way to make this the default tab?  I know about system-issuetabpanels-plugin.xml, where i can change default from "comments" to "all".  but, that doesn't seem to work for a non-JIRA tab like "Activity".

1 answer

0 votes
Susanne Götz [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 26, 2015

Hi Ming Ho,

the "Activity" tab is a JIRA feature, but it is possible that is was disabled in your instance.
Tempo Timesheets uses the JIRA worklogs database table to store worklogs, so all hours logged in Tempo will show in this tab, but no Tempo specific data (like information added as worklog attribute).

To view more information about the worklogs on an Issue including Tempo specific data, you will need to go to the Timesheet Report view. You can do this by clicking the "Report" button in the Tempo section of the Issue view. Please note that you need to be in the "Tempo Project Manager" role for the Project to view the worklogs of other users in the Timesheet view.

Regards,

Susanne Götz