Why I cannot see the Child-Progress bar on the Roadmap? I can only see the Epic bar

Sofia E Lizarraga April 26, 2022

Jira.png

1 answer

1 accepted

1 vote
Answer accepted
Dave Mathijs
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 26, 2022

Hi @Sofia E Lizarraga , welcome to the Atlassian Community!

When you click on View settings, do you have the option Progress under More details enabled?

Sofia E Lizarraga April 26, 2022

Screen Shot 2022-04-26 at 11.32.01 AM.png

Like Alex Stegani likes this
Sofia E Lizarraga April 26, 2022

Hi Dave, thanks for answering my questions, yes is enable , I took a screenshoot of the checkmark enable

Dave Mathijs
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 26, 2022

That was a wrong answer from me anyway.

The progress bar of the child issues are shown when an issue is added to an active sprint of a scrum board and determined by the start and end date of the sprint. You cannot change this for the standard issue types.

They progress bar of the child issues is not available for kanban board.

Dave Mathijs
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 26, 2022

Screenshot 2022-04-26 at 18.41.59.png

Sofia E Lizarraga April 26, 2022

Thank you very much Dave, for the orientation now I understand, why it didn't appear to me is that in other Gantt-type programs it did. good day thank you for your prompt response!

Sofia E Lizarraga April 26, 2022

Dave, sorry I have a question can I change my project to an active sprint?

Dave Mathijs
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 26, 2022

Just create a Scrum Board for your project, create a Sprint in the backlog, move an issue from an Epic to the sprint, start the sprint + set your start/end date and you're good to go.

Suggest an answer