Version/Epic Report do not obey boards Estimation setting

rwyborn September 8, 2019

Our projects have many long running tasks that are tracked via time spent being logged against them and remaining estimate updates. Hence our Jira board Estimation setting is configured to use "Remaining Estimate and Time Spent".

However the Version and Epic Reports appear to completely ignore this setting. They are only showing burnup based on Original Estimate when a task is completed.

This makes the reports completely useless when using "Remaining Estimate and Time Spent" Estimation for a board. Am I missing something here?

1 answer

0 votes
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 20, 2019

Hi rwyborn,

Thank you for reaching out to Atlassian Community!

I saw that you created a ticket with our support related to the same question, and as mentioned there, there is a feature request suggesting this:

I'm sharing here in case other community members face the same issue.

Regards,
Angélica

Suggest an answer

Log in or Sign up to answer