Unable to see story points upfront in backlog issue view of company managed project

Sravya
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 10, 2024

Hi all,

I recently made a company managed project by combining a few team managed boards. This is to have a single view of Frontend, Backend, Bug boards in one place. However, I am not able to see the story points in this combined view. I can view the story points of the same ticket in backlog view of the specific board but I am unable to see it here. PFA screenshot of the issue.

Screenshot 2024-10-10 at 4.52.08 PM.png

 

Some steps I tried:

  • I went to configure board of this and added story point estimate in the card layout but that is adding a new field in the card and not updating the values in story point field
  • This is also not showing me the sum of story points w.r.t status
  • PFA screenshot
  • In the screenshot, u can observe that new field is now shown on the cards on the left and the actual story point field which is on the right is still empty even for the tasks that have story point estimates filled in them. 

Screenshot 2024-10-10 at 5.02.29 PM.png

Can someone please help me in sorting out this issue

2 answers

2 accepted

1 vote
Answer accepted
Stephen_Lugton
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 10, 2024

@Sravya the team managed projects that I've looked at here all have Story Point estimate fields, rather than story point fields which is what the backlog view uses, so I think that that is your issue.

It's not possible to add the global story points field to the team managed projects so without converting / copying each of the team managed projects to a company managed project you won't be able to get the story points to show up on your backlog.

Sravya
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 11, 2024

ohh ok. Thanks for the clarification. This is very confusing, what is the use of having two different fields - story points and story point estimate. Hope JIRA makes a single field that can be used in team managed or company managed 

0 votes
Answer accepted
Marc - Devoteam
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 10, 2024

Hi @Sravya 

@Stephen_Lugton is right Team managed projects use a different story point field than team managed projects.