Hi all,
I recently made a company managed project by combining a few team managed boards. This is to have a single view of Frontend, Backend, Bug boards in one place. However, I am not able to see the story points in this combined view. I can view the story points of the same ticket in backlog view of the specific board but I am unable to see it here. PFA screenshot of the issue.
Some steps I tried:
Can someone please help me in sorting out this issue
@Sravya the team managed projects that I've looked at here all have Story Point estimate fields, rather than story point fields which is what the backlog view uses, so I think that that is your issue.
It's not possible to add the global story points field to the team managed projects so without converting / copying each of the team managed projects to a company managed project you won't be able to get the story points to show up on your backlog.
ohh ok. Thanks for the clarification. This is very confusing, what is the use of having two different fields - story points and story point estimate. Hope JIRA makes a single field that can be used in team managed or company managed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Sravya
@Stephen_Lugton is right Team managed projects use a different story point field than team managed projects.